| November - 2011 | |
| The driving wheels have been moved to the road leading off the turntable adjacent to the Black Python. It is imperative they are moved under cover as soon as possible, consequently a shelter has been ordered from Danport which should arrive by the end of November. The shelter procured should be large enough to accommodate work on the tender underframe. The design and acquisition file for the wheels was handed over to the Project by Dennis Howells on 12 November in a brief ceremony. LaDonna and a small team will handle all the cosmetic cleaning and bare metal protection at Didcot Railway Centre. | ![]() 12/12/2011 - Dennis Howells, Locomotive Manager & Wheels Contract Manager handing over the Project File for the wheels to Mike Cooper, Project Manager. |
A new workstream under Geoff Gore has been established to plan and oversee the re-wheeling of the chassis. As part of this process, measurement of and refurbishment of the main axleboxes is in hand. |
|
The wiping lubricator slots in bogie axleboxes are now being cleaned out, and minor repairs carried out, in preparation for final assembly. The spring hanger bolts have had their shafts bitumen coated, and the oil sump covers repaired and painted. |
|
![]() 19/11/2011 - Spring hanger bolts coated in bitumen. |
![]() 19/11/2011 - Completed locomotive vacuum reservoir. |
All major work on the reach rod has been completed, consequently it has been mounted on the frame. The last job is to locate the split pin hole in the wayshaft lever pin. |
|
![]() 19/11/2011 - The completed reach rod assembly. The bar below the reach rod, running parallel with and along the running plate is the front sandboxes linkage. The little excrescence to the right of the reach rod steady is an anti- bowing block present on all Lot 354 locomotives, but not shown on any drawings, but was put together by reference to photographs. |
|
Cleaning the front coupling hook, brake pull link, cylinder drain cock lever and reverser screw cover has also been undertaken. |
|
|
|




